The Quick Version
  • What happened: Gas South Arena in Duluth is in the middle of a $175 million rebuild that runs through early 2028. It includes a new entrance, new seats, bigger screens, suites and a 1,000-space parking deck.

  • The number that matters: $140 million. That is the part paid for with revenue bonds, which the AJC reports do not put taxpayers on the hook for repayment. The rest comes from the district's own cash reserves.

  • When it affects you: The new deck is due in early 2027. Then the arena goes fully dark for about 10 weeks next summer while crews replace every seat and put on a new roof.

Rendering of the redesigned west lobby at Gas South Arena

The redesigned west lobby, as planned. Rendering: Gas South District

The Math

Thirteen thousand seats. Every one of them is coming out.

Gas South Arena opened in 2003, and Gwinnett County owns it. Around it, the district has more than doubled the size of its convention center and opened the Westin Atlanta Gwinnett hotel in 2024. The arena is the piece being brought up to date now.

The plan starts at the front door. The lobby's curved wooden walls come out, and new security equipment gets built into a redesigned entrance. Inside come lobby bars, grab-and-go concessions and permanent merchandise stands. The seating adds loge seats, private suites, new low-level floor seats and a premium club sold through personal seat licenses. The video screens get bigger.

Rendering of grab-and-go concession stands on the Gas South Arena concourse

Concourse concessions after the renovation. Rendering: Gas South District

The catch is that you cannot swap 13,000 seats while people sit in them. Gas South District CEO Stan Hall put it bluntly to the AJC: without seats, the arena cannot operate "unless we have people bring a folding chair with them."

Who Wins, Who Pays
  • $175 million: the total, per Gas South District. Commissioners were told $170 million to $176 million when they signed on in July 2025.

  • $140 million: revenue bonds. Commissioners voted to issue them in November 2025, and the AJC reports they were issued in June 2026.

  • About $35 million: the remainder, from the district's internal cash reserves.

  • 1,000: spaces in the new parking deck, built by Brasfield & Gorrie and scheduled for the first quarter of 2027.

  • 10 weeks: the only full shutdown, next summer.

  • Early 2028: the target finish for the whole project.

Why This Matters

Who pays: Mostly the arena business itself. The bonds are revenue bonds, and the AJC reports taxpayers are not on the hook to repay them. The county is still in the deal: commissioners approved a resolution in July 2025 committing Gwinnett to partner with the Gwinnett Convention and Visitors Bureau, which runs the district, on the financing. Hall says signed agreements with Brasfield & Gorrie protect the price from inflation and trade disputes.

Who wins: Anyone who has missed a period standing in a concession line. Also the arena's teams: the Atlanta Gladiators in hockey, the Georgia Swarm in lacrosse and the Atlanta Vibe in women's pro volleyball. Hall told commissioners the arena has generated more than $1 billion in economic impact. The county's announcement does not say how that number was calculated.

Who carries the cost: Look at where the money goes. Loge seats, suites and a seat-license club are built for fans who spend more per ticket, and the district has not announced prices. The pressure behind all of this is competition. State Farm Arena is downtown, and new arenas are planned at North Point Mall and in Forsyth County, both chasing an NHL team. The upgrade is a bet that Gwinnett keeps its shows. It is also a $175 million bet that those shows don't move up the road.

Rendering of new loge seating at Gas South Arena

New loge seating, one of the premium products in the plan. Rendering: Gas South District

Rendering of premium suite space at Gas South Arena

Premium suite space, as planned. Rendering: Gas South District

What Happens Next

If you go to Gladiators games, concerts or graduations here, the next 14 months change how you get in, where you park and what a good seat costs.

  • Daily life: Events keep running through most of the work. Crews are working in phases to keep the arena open as many days as possible.

  • Money and options: New premium seats and seat licenses are coming. Prices are not public yet.

  • Disruption: About 10 weeks with no events next summer, dates to be announced. The 1,000-space deck is due before then, in early 2027.

The Bottom Line

The arena is phase one. Hall told the Atlanta Business Chronicle on Nov. 11 that a developer for the wider campus, which is planned for restaurants, apartments, shops and offices, could be named soon. Arena and campus deals go through the Board of Commissioners. Its next business session is Dec. 1.

One question for you: what is the one fix that would get you to more events at Gas South? Hit reply. We will pass the answers along.

What's Happening

In plain English: Gwinnett owns a 13,000-seat arena that opened in 2003. The group that runs it is borrowing $140 million and spending about $35 million of its savings to modernize the building, add parking and sell more premium seats. It will close the arena for one stretch next summer to do it.

$175 million to stay in the game. Gas South is betting fans will pay more for a better seat before new arenas up the road give them somewhere else to go.

Loop Wallet — free local perks in your phone

Your Gwinnett perks, in your phone.

The Loop Wallet is a free membership pass for Apple and Google Wallet. Claim local offers from Gwinnett partners, then show your QR code at the counter to redeem.

Not a member yet? Subscribe to The Gwinnett Loop. Want your business in front of Gwinnett? Partner with us.

No spin. Just Gwinnett.

Original Articles

  1. Gwinnett County: Board of Commissioners commits financial support for major Gas South Arena renovation (July 2025)
    Read on gwinnettcounty.com

  2. Gas South District: Gas South Arena breaks ground on $175 million renovation project
    Read on gassouthdistrict.com

  3. Atlanta Journal-Constitution: Gas South Arena begins $175M renovation, but don't expect it to shut down
    Read on ajc.com

  4. WSB-TV: Gas South Arena set for $175 million makeover with new suites, parking deck
    Read on wsbtv.com

  5. Metro Atlanta CEO: Gwinnett commissioners to issue bonds for Gas South Arena renovations (Nov. 2025)
    Read on metroatlantaceo.com

  6. Connect CRE: Gwinnett County advancing $175M arena improvements
    Read on connectcre.com

  7. North Atlanta Star: Gas South Arena's $175 million renovation comes with bigger plans for the campus
    Read on northatlantastar.com